Track and Analyze Projects › Analyze Projects › Analyze Projects with Earned Value Variances › Percent Complete Indices
Percent Complete Indices
Use the % Complete Calculation Method field (on the Description tab of the Project Properties dialog box) to specify how Open Workbench computes the percent complete value. Earned value data is used against the Budget at Completion (BAC) to calculate the percent complete indices.
The percent complete value is used in earned value calculations such as the following:
- Budgeted Cost of Work Performed (BCWP)
- Cost Variance (CV)
- Cost Variance Index (CVI)
- Schedule Variance (SV)
- Schedule Variance Index (SVI)
- Schedule Variance Performed (SVP)
- Cost Performance Index (CPI)
- Budgeted Cost of Work Scheduled (BCWS)
- Actual Cost of Work Performed (ACWP) as a percent of the baseline budget
Periodic reviews of these measures can help you uncover trends over time as your project progresses. Examples of percent complete index fields include Perform % Complete, Schedule % Complete, and Actual % Spent.
To view this data, first add the field to a view.
More information:
Analyze Projects with Earned Value Variances
Define Project Description Properties
Define Open Workbench Default Options
Analyze Projects with Earned Value Variances
View Task Percent Expended Amount
|