Add Entries to a Timesheet Manually

To add timesheet entries to your timesheet manually, use the Add Task, Add Other Time, and Add Indirect Row buttons. These buttons display on the timesheet page. To view the page, open your timesheet.

You can add a task to your timesheet for time spent on assignments that are not in the project plan. Use indirect timesheet entries when you want to log time directly against a charge code. Indirect timesheet entries contain predefined, general descriptions and input type codes. You can select the indirect entry that best suits the work you performed.

The time you spend on indirect task entries is not counted as part of the project plan. The project manager converts the indirect entry into a project task by adding it to the project plan.

Follow these steps:

Project Task Entries

Click Add Task. Newly added tasks display under the Tasks category in the timesheet list.

Other Time

Click Add Other Time. Newly added rows display under the Other Time category in the timesheet list.

Incidents associated to an investment

Click Add Incident. Newly added incidents display under the Incidents category in the timesheet list.

Indirect timesheet entries

Click New Indirect Row. Newly added indirect entries display under the Indirect category in the timesheet list.