This section discusses the Timesheet Overview section of the Resource Management menu and the Timesheet Review action on the Team tab of projects. The pages and portlets in this section display information about the actual and planned time spent on investments.
Use timesheets to record time worked on assignments. For projects, time is recorded at the task level by period. For investments, time is recorded to an effort task by period.
Timesheets track time at the task level on a daily basis. The time entries for a resource are recorded at the task level based on the duration of the task and the overall duration of the project or other investments. The timesheet actuals are generated from the approved hours that project team members record on timesheets.
Once approved, the Post Timesheets job runs to post the timesheets. The job updates the Actuals value on the resource assignment properties page. The job also processes the actuals (the recorded number of hours worked) against a resource task assignment. Posting also updates the remaining work or ETC. Project managers can compare the actuals with estimates and modify their plans as needed.
Use the Timesheet Overview page to review summary and detailed information about team timesheets and any modified estimates entered by the team members. To access this page, open Home, and from Resource Management, select Timesheet Overview.
This page includes the following portlets:
Use the page-level filter to filter all portlets at once by investment OBS, investment manager, employment type, timesheet status, and timesheet period.