Depending on whether more or less time is required for a task, a team member can increase or decrease the ETC on a task. They can do this using Timesheets. However, the project manager must approve these modifications before the change is reflected in CA Clarity PPM.
The Pending Estimates Review portlet displays pending estimates and recommended changes by project, task and resource. Use this portlet to compare pending estimates to planned estimates by task and by resource.
This portlet displays the following fields:
Displays the project name. Click a project name to view the project properties.
Displays the name of the task. Click a task name to view the task properties.
Displays the name of the resource assigned to the task. Click a resource name to view the resource assignment properties page.
Displays the start date of the task assignment.
Displays the finish date of the task assignment.
Displays the ETC amount that was added to the timesheet.
Displays the ETC amount that was initially assigned to the task.
Displays the amount of unposted actuals for the task.
Displays the adjusted plan ETC amount.
Formula: (Plan ETC – Pending Actuals)
Displays the ETC amount that is the recommended change to the current Plan ETC.
Formula: (Pending ETC – Adjusted Plan ETC)
Displays a stoplight indicating the recommended change in ETC.
Stoplights: