Work Packages (WP)

Work packages represent the actual work associated with a deliverable. Work packages are associated with control accounts. Create the packages as part of the bidding process to establish your initial contract baseline for cost.

Some work packages are linked to project or project tasks. Earned value from the project or task is updated. Then, rolled up to the work package when the Update Earned Value Totals - Contracts job and the Update Earned Value History - Contracts jobs run.

This section contains the following topics:

How to Work with Work Packages

Work Package Types

Planning Work Packages

Create Work Packages for Control Accounts

View a List of and Open Work Packages

Edit Work Packages

Link Work Packages to Projects or Project Tasks

View Work Package Earned Value Data