Save Existing Projects as New Projects

You can save a copy of an existing CA Clarity PPM project as a new project. When you save a copy as a new project, all project information is copied to the new project. Both projects exist independently of each other. No file sharing occurs.

If you save a copy of a CA Clarity PPM project, your lock on that project is discarded unless you recently saved it as an .MPP file.

Once you have saved a copy of the project, you can open the new project to update it.

To save a copy of project as a new project

  1. Open the project in Microsoft Project from CA Clarity PPM.

    The project opens.

  2. Select Save As To CA Clarity PPM from the CA Clarity PPM Integration toolbar or menu.

    The Save As dialog box appears.

  3. Enter a new, unique CA Clarity PPM project ID, and then click Save As.

    A copy of the project is saved as a new project in CA Clarity PPM.

More information:

Open Projects from CA Clarity PPM