Manage Automated Requisition Processes

In the out-of-the-box notification system for requisitions, notification generation depends on manually changing the Status setting of the requisition. If the setting is not changed, a notification won't be sent. This is particularly true for new requisitions—if their status is not changed to "Open," recipients won't know that a new requisition has been created and needs to be filled.

You can avoid notification uncertainty by setting up an automated notification process that identifies different stages in a requisition's lifecycle. An automated process can issue a notification whenever a new stage is reached. Use the Requisition: Processes page to do this.

When you create a process from within a requisition, it will be available only for that requisition. When your administrator creates a global requisition process in the Administration Tool, the process is available for use by all requisitions. Global access rights are required to create a global process.

The Requisition: Processes page contains two links:

To access resource requisition processes

  1. Select Resource Requisitions from the Resource Management menu.

    The Resource Requisitions page appears.

  2. Open the requisition for which you want to create, run, or view a requisition process.

    The Requisition Properties page appears.

  3. Click the Processes tab.

    The Requisitions: Processes page appears.

More information:

Create Processes for Requisitions

Track the Progress of Processes

Delete Processes