Subnets are a set of project tasks that have dependencies among themselves, or a single task with no dependencies. During Autoschedule, you can choose to calculate and display separate critical paths for each subnet and for each task that does not have dependencies. Otherwise, only one critical path, the longest path, is calculated for the project.
There are several key benefits to scheduling subnets:
To schedule subnets during Autoschedule
The Project: Properties: Main - General page appears.
The Project: Properties: Main - Schedule page appears.
The Autoschedule page appears.
Your project is set up to calculate separate critical paths and separate critical paths are calculated for your project.