Important! Before applying top-down estimating, make sure that for each task you want to share a portion of the top-down distribution, you enter the percentage of the top-down estimate distributed to the task.
To apply top-down estimating
The Project: Properties: Main - General page appears.
The Project: Properties: Main - Estimating page appears.
Defines the mode for estimating.
Value: Top-Down Estimating
Defines the amount of ETC you want to distribute.
The ETC is distributed to the tasks set up to receive the top-down distribution.