When you change the ETC value at the project level, CA Clarity PPM distributes the value across all of the project's tasks according to task duration, resource availability, and the percentage of time the resource is allocated to the task. The current ETC assumes the new value.
To apply a new ETC across all of the project's tasks
The Project: Properties: Main - General page appears.
The Project: Properties: Main - Estimating page appears.
The new ETC is applied.