Apply New ETC Across Project Tasks

When you change the ETC value at the project level, CA Clarity PPM distributes the value across all of the project's tasks according to task duration, resource availability, and the percentage of time the resource is allocated to the task. The current ETC assumes the new value.

To apply a new ETC across all of the project's tasks

  1. Open the project to which you want to edit tasks.

    The Project: Properties: Main - General page appears.

  2. Select Estimating from the content menu.

    The Project: Properties: Main - Estimating page appears.

  3. In the New ETC field, enter in the new estimate you want to apply across all of the tasks in the project, and click Apply.

    The new ETC is applied.