Performance Measurement Baselines

Contract baselines are snapshots of the contract's total effort and total costs at the moment of capture. This snapshot includes the effort and cost for all control accounts and summary level planning packages associated with the contract work breakdown structure (CWBS).

The control account's baseline is the summary of the baseline data for each of the control account's work packages.

A contract baseline:

The Baseline at Completion (BAC) is calculated and stored with and without burdens. Earned value is calculated on unburdened BAC and contract pricing is shown by using the burdened BAC costs. Total Burdened BAC is calculated using the following formula:

BAC = (Cost of Actual Work + Burdened Cost) + (Cost of Remaining Work + Burdened Cost)
Baseline Currency

When baseline and earned value metrics are calculated for a contract, the data is calculated and written to the contract baseline and contract earned value history tables using the contract's currency.

Baselines and Work Packages

When you create a contract baseline, you automatically create a project-level baseline for those projects that are associated to the contract via work packages. You create the association by linking the work package to the project or by linking it to the project's tasks.

More information:

Create New Contract Baselines

Link Work Packages to Projects or Project Tasks

Burdening

Contract Pricing