Resources and Roles › Calendars, Shifts, and Work Days › Define Work Days in Calendars
Define Work Days in Calendars
You can designate workdays and non-workdays.
Follow these steps:
- Open Administration, and from Project Management, click Base Calendars.
- Click the name of the calendar.
The edit calendar exceptions page appears.
- Select the month at the top of the calendar.
- Indicate which days are standard workdays.
- To select dates by days of the week, select the check box next to the day of the week and click Make Workday.
- To change dates from workdays to non-workdays, select the check box next to each date. Click Make Non-Workday.
- (Optional) When you change a specific holiday on the resources calendar to a nonworkday, the shift information or availability is removed. If you change the day back to a workday, a check is made to see if a shift pattern exists for that day in that calendar (or parent). One of the following actions occurs:
- If a shift pattern does exist for that day, the day is set to use that shift pattern.
- If a shift pattern for the day does not exist, a check is made for a shift pattern for the corresponding day of the week for that calendar (or parent, as needed).
- If a shift pattern is found from the search, the day is set to use that shift pattern.
- If no shift pattern is found for that specific day of the week, then the first day of the week shift pattern that is found is used starting with the first day of the week (Sunday).
- If no shift pattern exists for any day of the week, then the default shift patterns of 8:00 AM – 12:00 PM and 1:00 PM – 5:00 PM are set for that day.