Follow these steps:
The list page appears.
The select page appears.
The create project page appears.
Defines the name for the project.
Limits: 80 characters
Required: Yes
Defines the unique identifier for the project that is typically auto-numbered.
Limits: 20 characters
Required: Yes
Displays the date of starting the project.
Displays the date of completing the project.
Defines the objectives for this project.
Limits: 200 characters
Indicates the status of the task.
Values: Started, Not started, and Completed
Indicates the level of work that is completed on the tasks.
Values:
Default: Not Started
Required: Yes
Specifies the pool of resources allowed when assigning resources to projects.
Values:
Specifies the dashboard view selected for the project. Click the drop-down to select a view option.
Example: Use Project Default Layout value to view the default labor and team utilization charts on the project dashboard page.
Values: PMO-Project Status, PMO-Program Status, PMO-Project Storyboard, Program Layout, or Project Default Layout
Default: Project Default Layout
Defines the method to use for calculating percentage completion of tasks on this project.
Values: Manual, Effort, Duration
Defines the organizational OBS associated with the project.
Defines the departmental OBS associated with the project.
Displays the name of the template.
Defines the percentage of increase or decrease in the work estimates on each task for the new project, relative to the template.
Default: Zero percent means no change
Defines the percentage (positive or negative) as the scaling factor for the dollar amounts defined in project cost plans and benefit plans.
Default: Zero percent means no change
Select the option to convert all resources from the project template into roles in the new project.
Default: Cleared
The project is created.
|