Map CA Clarity Agile Task Types to CA Clarity PPM Charge Codes

If you have assigned charge codes to your project tasks in CA Clarity PPM, you can map these charge codes to the CA Clarity Agile task types. Mapping the task types to charge codes allows you to assign appropriate charge codes to actuals on linked tasks. A project manager can also map task types to charge codes and run the Populate CA Clarity Agile Task Types process, if they have the following global and instance access rights:

Best practices:

Follow these steps:

  1. In CA Clarity PPM, open the linked project.

    The project properties appear.

  2. Click Agile Task Type Mapping from the content menu.

    The CA Clarity Agile task type and charge code mapping page appears.

  3. Click New.

    The create mapping page appears.

  4. Complete the following fields and submit:
    Task Type

    Defines the CA Clarity Agile task type for a task.

    Charge Code

    Defines the CA Clarity PPM charge code for the same task.