Disable Change Management for Requirements

Disable change management for requirements to discontinue using the approval process. When you disable change management for requirements, a background job automatically approves all pending requests.

Follow these steps:

  1. Click Administration, and from Configuration, click Global Configuration.
  2. Clear the Requirement Change Management checkbox.
  3. Save your changes.

    The background job begins approving requirements that have been submitted for approval. You receive an email notification when the job completes. The following changes occur for approved requirements: