Manage Tasks on the Virtual Wall

As a product owner or a product team member, you can create tasks on the Virtual Wall. If you are not a product team member, you can only view the Virtual Wall.

Follow these steps:

  1. Click Agile, and from Sprint Tracking, click Virtual Wall.
  2. Click New Task for the user story to which you want to add a task.
  3. Enter the requested details.
  4. Save your changes.

    A new task card is created on the virtual wall.

Note: To edit, delete, or create new impediment on the virtual wall, click the arrow on the task card, and click Edit, Delete, or New Impediment.

The Virtual Wall enables you to drag-and-drop tasks to update their status. Dragging a task to a new status changes only the status. Edit the task to update the hours that are completed on it to reflect the burndown accurately. However, when you drag a task to a Closed status, any remaining hours on the task are zeroed out automatically.