The Agile Timesheet Sync job populates the following items in CA Clarity™ PPM from CA Clarity™ Agile task work logs:
Each time the Agile Timesheet Sync job runs, this job overwrites any changes to timesheets made in CA Clarity™ PPM provided the timesheet is still open.
Best Practice: Make all your updates in CA Clarity™ Agile and the changes are updated in the CA Clarity™ PPM timesheet the next time the Timesheet Sync job runs. You do not need to update the CA Clarity™ Agile tasks in the CA Clarity™ PPM timesheet.
|