Schedule an Object

To schedule an object

  1. In the Folders management area of the CMC, select an object.

    Note: To change the default schedule settings for the object, click Default Settings when you open the Schedule dialog. Set the scheduling settings and click Save.

  2. Click Actions, Schedule.

    The Schedule dialog displays, showing the default settings for the object.

  3. Enter an appropriate instance title.
  4. Click Recurrence and select the recurrence pattern you want.

    For example, select Weekly.

  5. Specify the Run option and parameters that you want.

    For example, select Weekly and then specify Monday, Wednesday, and Friday.

  6. Set any of the other schedule options and parameters as required.
  7. Click Schedule.

    The system creates a scheduled instance and runs it according to the schedule information you specified. You can view the scheduled instance on the History page for the object.