3.3 Management Objective Reports


Management objective reports are produced daily, weekly, and
monthly as a standard output of the CA MICS operational jobs.
The reports available from the CA MICS Analyzer Option for
VSE/POWER are listed in Figure 3-13.



ANALYZER OPTION FOR VSE/POWER

MANAGEMENT OBJECTIVE REPORTS

+---------------------------------------------+-----------------------------+----------------+

| Report Name | Time Produced | Macros Used * |

| | | | | |

| | Daily | Weekly | Monthly | |

+---------------------------------------------+-----------------------------+----------------+

| | | |

| VSE/POWER Job Initiation Objective | YES | PWRDLHR PWRDHHR|

| | | PWRPTR PWRJSAX|

| | | |

| | YES | PWRWLHR PWRWHHR|

| | | PWRPTR PWRJSAX|

| | | |

| | YES | PWRLOZN PWRHIZN|

| | | PWRMPTR PWRMJSX|

| | | |

| VSE/POWER Job Turnaround Objective | YES | PWRDLHR PWRDHHR|

| | | PWRMREF PWRJMAX|

| | | |

| | YES | PWRWLHR PWRWHHR|

| | | PWRMREF PWRJMAX|

| | | |

| | YES | PWRLOZN PWRHIZN|

| | | PWRMREF PWRJMAX|

| | | |

| VSE/POWER Job Group Turnaround Received | OPT | PWRDLHR PWRDHHR|

| | | PWRMREF PWRJMAX|

| | | |

| | OPT | PWRWLHR PWRWHHR|

| | | PWRMREF PWRJMAX|

| | | |

| | OPT | PWRLOZN PWRHIZN|

| | | PWRMREF PWRJMAX|

| | | |

+---------------------------------------------+-----------------------------+----------------+


* - Macro descriptions are provided in Section 3.4 of this guide.
OPT - This report must be must be user tailored and activated as described in Section 3.4.

Figure 3-13.  Management Objective Reports, Analyzer Option for VSE/POWER


The daily report tracks activity by hour within the day.  The
weekly report tracks activity by hour within day for a full
week.  The monthly report tracks activity by zone within
month.

The following fields are used, depending on the report
version:

HOUR:        The hour of the day.

REPTDATE:    The date reported.

ZONE:        The time zone (shift).

YRMONTH:     The year and month reported.

In each case, the report is produced as a vertical bar chart,
with response on the vertical axis.  Depending on the hour
range you select, the report may be produced as a horizontal
bar chart instead (see Section 3.4 for more information).

The following sections describe the management objective
reports:

    1 - VSE/POWER Job Initiation Objective
    2 - VSE/POWER Job Turnaround Objective
    3 - VSE/POWER Job Group Turnaround Received