Dynamic Changes to Special Day Classes

Because Special Day Restrictions are taken into account only when calculating a job’s next scheduled start time, and a job’s next scheduled start time is only calculated when a job is run, any changes made to a job’s Special Day Restrictions will not take effect until the next time a job is run and its next scheduled start time is calculated. Thus, creating Special Day Restrictions for a job, adding or deleting Special Day Classes from a job’s Special Day Restrictions, or modifying the contents of a Special Day Class will not change a job’s current scheduled run time. These changes will take effect the next time the job is run and its next start time is calculated.