How to Migrate CA Identity Manager on a JBoss Cluster

Changing to a new version of JBoss requires a migration of the CA Identity Manager server, including steps for uninstalling the CA Identity Manager server, installing the new version of the CA Identity Manager server, then migrating the data.

The following procedures describe how to set up multiple JBoss application servers with the same CA Identity Manager application on each server. In this type of cluster, each JBoss application server acts independently of the other application servers, but they share the load through JMS messaging.

Step

 

1. Uninstall the CA Identity Manager server.

 

2. Test the default mulitcast address.

 

3. Create the master node.

 

4. Add cluster nodes.

 

5. Configure the JK connector.

 

6. Upgrade the workflow database. (if upgrading from r12)

 

7. Migrate task persistence data. (if upgrading from r12)