Symptom:
On the Scheduled Reports tab, Report Scheduling subtab, you can view all scheduled jobs with their status. The Status column displays Generating during the process of report generation and Scheduled when the job is scheduled. After an upgrade from the base r12.0 GA version, the Status column for reports is cleared, regardless of the status. When a scheduled report is regenerated, its Status is again displayed.
Solution:
The omission of a value in the Status column for a scheduled job is a temporary display issue. Take no action. The correct status will display the next time the report is generated.
| Copyright © 2010 CA. All rights reserved. | Email CA about this topic |