View Tasks Marked as Key Tasks

A key task is a task that you consider being of key importance to the project. When you mark a task as a key task, its status does not impact any other Open Workbench behavior. Use the Key Tasks tab on the Project Properties dialog to:

To edit a key task, edit the task's fields in a spreadsheet view, such as the Gantt Chart view.

Follow these steps:

  1. Click Project Properties in the application menu.
  2. Open the Key Tasks tab.
  3. View the following key task data, and click OK:
    ID

    Defines the key task's external ID.

    Name

    Defines the key task's name.

    Status

    Defines the key task's status.

    Values: Not started, Started, or Completed

    Project

    Defines the project name that is associated with the key task.

    Finish

    Defines the date the key task is scheduled to finish.

    Note: You can edit the finish date provided you have not assigned a resource to the task and the task is a fixed duration task.

    Baseline Finish

    Defines the date the key task is scheduled to finish based on the current baseline.

More information:

How to Update the Project Data

Task Status and Percent Complete