Define the Description Properties

Use the Description tab on the Project Properties dialog to enter or edit project administrative details.

Follow these steps:

  1. Click Project Properties in the application menu.
  2. Complete the fields in the Description tab. The following fields require explanation:
    Department

    Defines the department responsible for the project.

    Budget

    Defines the project estimated budgeted amount.

    Description

    Defines the project description.

    % Complete Calculation Method

    Specifies the method for calculating the % Complete value for the project and the associated tasks.

    Values:

    • Manual. Use this method if you want to enter the % Complete value for the project and for tasks at any level in the WBS manually.
    • Duration. Use this method if you track % Complete for the project and for summary tasks based on duration. Completed Duration is the percentage of the task duration that is considered to be complete. Completed Duration for a summary task is the sum of (% Complete * Duration) for all descendant detail tasks. Total Duration is the sum of the duration for all descendant detail tasks. You manually enter the percent complete value for detail tasks. The % Complete is automatically calculated based on the following formula:
      % Complete = Completed Duration / Total Duration
      
    • Effort. Use this method to calculate the % Complete for all tasks automatically. Labor Actuals is the sum of all actuals posted for labor resources. Labor Estimates is the sum of all ETC for these resources. The % Complete is automatically calculated based on the following formula:
      % Complete = Labor Actuals / (Labor Estimates + Labor Actuals).
      
  3. Click OK.

More information:

How to Update the Project Data

Percent Complete Indices