Previous Topic: Current Issues Drill Down Page

Next Topic: Staffing Outlook Drill Down Page

Staffing Portlet

The Staffing portlet lets you identify projects where resources are not assigned to tasks within the days outlook. The portlet displays in a bar chart format the unstaffed ETC hours, which are hours assigned to a role instead of a resource. The Y-axis of the chart displays project names. The X-axis displays the number of hours assigned to roles instead of resources for each project.

Summary tasks and milestones are not included in this portlet. Also, tasks with a status of "Completed" are not included in this portlet.

The portlet helps you identify projects with tasks where resources are not assigned. You can analyze the results and replace roles with resources that can complete the work. Click a bar on the graph to go to the Staffing Outlook Drill Down page. The Staffing Details portlet displays on this page.

More information:

Staffing Outlook Drill Down Page