Schedule Performance Portlet

The Schedule Performance portlet displays the number of late tasks categorized as critical late, past due, or scheduled late within the days outlook as follows:

Summary tasks and milestones are not included in this portlet. Also, tasks with a status of "Completed" are not included in this portlet.

Tasks are considered late if they have a days late value, which is calculated as follows:

No columns on the graph imply that all the tasks within the days outlook are completing as scheduled.

Click a bar on the graph to go to the schedule performance drill-down page. The Schedule Performance portlet displays on this page.