The Milestones portlet provides a list of project milestones and schedule indicators within the days outlook.
The portlet includes the following fields:
Displays an icon that links to the properties page of the project.
Displays the name of the project. Click a project name link to go to the project dashboard.
Displays the milestone name. Click the name of the milestone to go to the task properties page.
Displays the finish date for the milestone to be complete.
Displays a stoplight indicating days late as a percentage of the summary task or project timeframe, which is finish date minus start date. If the milestone has a parent task in the WBS, then the parent task timeframe is used in the calculation. If the milestone is at the top level of the WBS and does not have a parent task, then the project timeframe is used in the calculation.
The calculation takes into account the milestone status and baseline (if a baseline exists). The color of the stoplight indicates if the milestone is on schedule or late.
Stoplights:
Displays the number of days late considering the following:
If a baseline exists, then days late is calculated as milestone finish date minus baseline finish date. A positive number indicates that the milestone is late according to the baseline. A negative number indicates that it is early according to the baseline.
If a baseline exists and the milestone finish date is the same as the baseline finish date, then the milestone is considered late if it is not completed and it was due before today’s date. In this case, days late is calculated as today’s date minus milestone finish date.
If there is no baseline, then days late is calculated if the milestone is not completed and it was due before today’s date. In this case, days late is calculated as today’s date minus milestone finish date.
The following fields are available for this portlet and you can add them through the configure option:
See the Personalizing CA Clarity PPM User Guide for more information.
Displays the milestone start date.
Displays the milestone baseline start date.
Displays the milestone baseline finish date.
Displays days late as a percentage of the summary task or project timeframe, which is finish date minus start date. If the milestone has a parent task in the WBS, then the parent task timeframe is used in the calculation. If the milestone is at the top level of the WBS and does not have a parent task, then the project timeframe is used in the calculation. The calculation takes into account the milestone status and baseline (if one exists).
Displays a stoplight indicating the number of days a milestone is late, considering the milestone status and whether or not a baseline exists for the milestone. The color of the stoplight indicates if the milestone is on schedule or late.
Stoplights: