The Cost and Schedule Overview portlet shows metrics, performance indicators, and risk information of each project associated to a program. Use this portlet to analyze the performance of ongoing projects.
The following fields display on the portlet:
Displays an icon that links to the project properties page.
Displays the project name. Click a project name to view the project dashboard.
Displays the system-calculated value of baseline at completion, which is the baseline cost at the time of the current baseline revision.
Source: Schedule & Performance properties page of the project.
Displays the system-calculated value of actual cost of work performed (ACWP), which is the total direct cost incurred in performing work based on posted actuals.
Source: Schedule & Performance properties page of the project.
Displays the system-calculated value of estimate at completion, which is the total cost of actual work completed to date and the predicted cost of finishing the remaining work.
Source: Schedule & Performance properties page of the project.
Displays the variance between the estimated plus actual cost and the baseline cost.
Source: Schedule & Performance properties page of the project.
Formula: ((ETC Cost + Actual Cost (ACWP)) - BAC Cost)
Displays a stoplight indicating the projected cost variance as a percentage of BAC cost.
Source: Schedule & Performance properties page of the project.
Formula: (((ETC Cost + Actual Cost (ACWP)) - BAC Cost) / BAC Cost) * 100
Stoplights:
Displays the start date of the project.
Displays the finish date of the project.
Displays the baseline finish date of the project.
Displays a stoplight indicating days late as a percentage of the project timeframe, which is finish date minus start date. The calculation takes into account the project progress and baseline (if a baseline exists). The color of the stoplight indicates if the project is on schedule or late.
Stoplights:
Displays the number of days late considering the following:
If a baseline exists, then days late is calculated as project finish date minus baseline finish date. A positive number indicates that the project is late according to the baseline. A negative number indicates that it is early according to the baseline.
If a baseline exists and the project finish date is the same as the baseline finish date, then the project is considered late if it is not completed and it was due before today’s date. In this case, days late is calculated as today’s date minus project finish date.
If there is no baseline, then days late is calculated if the project is not completed and it was due before today’s date. In this case, days late is calculated as today’s date minus project finish date.
Displays a stoplight based on the project risk score. The project risk score determines the color of the stoplight.
Displays the total number of high-priority risks. Risks are not included if their status is “Resolved” or “Closed”.
Displays the total number of high-priority issues. Issues are not included if their status is “Resolved” or “Closed”.
Displays the total number of high-priority change requests. Change requests are not included if their status is “Resolved” or “Closed”.
The following aggregated amounts appear at the bottom of the portlet:
Displays the total BAC cost, actual cost, EAC cost, and projected cost variance for the projects associated to the program.
Displays the program budget cost.
Displays the difference between the program budget and total project EAC costs. A negative variance value indicates the program is over budget.
The following fields are available for this portlet and can be added through the configure option:
See the Personalizing CA Clarity PPM User Guide for more information.
Displays the project baseline start date.
Displays how well the project aligns to the organization business goal. The higher the business alignment value is, the stronger the alignment.
Stoplights:
Displays the system-calculated value of the baseline effort (actuals plus remaining ETC) at the time of the current baseline revision.
Source: Schedule & Performance properties page of the project.
Displays the system-calculated value of the actual effort posted for the tasks in the project.
Source: Schedule & Performance properties page of the project.
Displays the system-calculated value of the estimated effort to complete the project.
Source: Schedule & Performance properties page of the project.
Displays the system-calculated value of the estimated effort at completion (actuals plus remaining ETC) of the project.
Source: Schedule & Performance properties page of the project.
Displays the variance between EAC effort and baseline effort.
Source: Schedule & Performance properties page of the project.
Formula: (EAC Effort – BAC Effort)
Displays a stoplight indicating the projected effort variance as a percentage of BAC effort.
Source: Schedule & Performance properties page of the project.
Formula: ((EAC Effort – BAC Effort) / BAC Effort) * 100
Stoplights:
Displays the planned benefit of the project.
Displays the planned cost of the project.
Displays the system-calculated value of budgeted cost of work scheduled (BCWS) or the budgeted amount you can spend on the project in a given time. If time is not specified, either the current date for the project or the system date is used. BCWS is also referred to as the planned value (PV).
Source: Schedule & Performance properties page of the project.
Displays the system-calculated value of budgeted cost of work performed (BCWP). The value is calculated and recorded when you baseline a project, or when you update earned value totals. BCWP is also referred to as the earned value (EV) and represents the amount of baseline cost (BAC) completed based on performance. Performance is measured using the Task EV Calculation method.
Source: Schedule & Performance properties page of the project.
Displays a stoplight based on the number of days a project is late, considering the project progress and whether or not a baseline exists for the project. The color of the stoplight indicates if the project schedule is on schedule or late.
Stoplights:
Displays days late as a percentage of the project timeframe, which is the finish date minus the start date. The calculation takes into account the project progress and baseline (if a baseline exists). The days late percentage shows the proportion by which a project is late. One day late in a six-month project does not have the same impact as one day late in a one-month project.
| Copyright © 2012 CA. All rights reserved. | Tell Technical Publications how we can improve this information |