Track Projects by Total Actual Usage

Use the total actual usage tracking method to track projects based on actuals, pending actuals, and estimate to complete (ETC) entered in Open Workbench for each resource assigned to a task.

If you are using Open Workbench with CA Clarity PPM, as resources enter hours on their CA Clarity PPM timesheets, you can view pending actual hours in the Open Workbench project plan.

More information:

How to Track Projects

Define Time Scales

How to Enter Pending Estimates

Display Pending Estimates Data in Views

Accept Pending Estimates

Reject Pending Estimates

Refresh Project Data