After you create a project task, you can change its position in a spreadsheet view that displays the task detail pane, such as the Gantt Chart view.
Note: If you move a task to an empty location that is within a sub-project or after the last line of a sub-project, the task becomes part of that sub-project.
To change the location of a task
The task is selected and is ready to be moved to its new location on the WBS.