About Analyzing Data in Multiple Baselines

You can create a baseline with which to analyze the impact of the additional work. When you select only a few of the project tasks and baseline, the baseline values are updated for those tasks. The summary level baseline information remains the same until you update the baseline for the selected summary task, or the entire project. Use the summary level baseline to analyze the changes that have occurred at that level, even though they do not show at the task level.

More information:

Multiple Baselines with Master Projects and Subprojects

Set Multiple Baselines

Rebaseline Projects

Track and Analyze Projects

About Analyzing Projects with Current Baseline