You can display one baseline in a view at a time. To view baseline information, you must first include the fields that display baseline data in one of your views. You can display the current baseline in a spreadsheet view, such as the Gantt Chart view, against the current status of the project. Special baseline markers on Gantt bars indicate the baseline information to differentiate the baseline information from the current schedule.
To include the fields that display baseline data in a view
To display a baseline
The Gantt dialog box appears.
The baseline markers appear next to the Gantt bars on the Gantt chart.