Previous Topic: How to Track Resources

Next Topic: Track Resources by Periodic Actual Usage

Track Resources by Total Actual Usage

You can record periodic actual usage using the Resources tab on the Task Properties dialog box or by editing a view that displays the Actual field name.

To record total actual usage in a view

  1. From a view that displays the task detail pane, select a task and click in the cell displaying total actual usage.
  2. Enter the total actual usage for each applicable cell on the timescale.