Delete Baselines (Contracts)

Deleting the current baseline and with another baseline revision existing, the remaining baseline becomes the current revision. You require to have the Contract - Baseline Delete access right to delete contract baselines.

Follow these steps:

  1. Open the contract.

    The properties page appears.

  2. Click Baseline.

    The baseline properties page appears.

  3. Select the check box next to the baseline, and click Delete.

    The confirmation page appears.

  4. Click Yes.