By Example: Create Two Allocation Curves

You have a resource with default allocation set at 100 percent. You booked this resource to work on your project from 8/10/12 through 11/10/12. But the resource is also scheduled to work on another project 50 percent of the time through 9/1. In addition, the resource plans to be on vacation from 9/15 through 9/22. In this case, you create two allocation curves for the resource: one that indicates a deviation to 50 percent from 8/01/12 through 9/01/12, and another that indicates a deviation to 0 percent from 9/15/12 to 9/22/12.