Resource Planning › Edit Resource Allocations › How to Work with the Booking Status Portlet › Change Resource Booking Status
Change Resource Booking Status
You can change booking status on an investment for a resource.
Follow these steps:
- With the resource/role allocations open, click in the field containing the data and edit the data.
- Booking Status
-
Defines the booking status for the resource.
Values:
- Soft. The resource is tentatively scheduled to work on the investment.
- Hard. The resource is committed to work on the investment.
- Mixed. The resource is both soft and hard allocated to the investment or the soft allocation for the resource does not match the hard allocation.
Default: Soft
Required: Yes
- Click Save.