Define Scheduling Properties

Follow these steps:

  1. Open the release.

    The general page appears.

  2. Open the Properties menu, and click Main, then from Properties, Schedule.

    The schedule page appears.

  3. Define the following fields, and save:
    Start

    Defines the scheduled start date of the release.

    Finish

    Defines the scheduled finish date of the release.

    Alpha

    Defines the alpha start date of the release.

    Beta

    Defines the beta start date of the release.

    Release to Market

    Defines the scheduled date of release to the market.