Define the release effort properties using the Effort section on the release properties page. The section displays the budgeted effort data that you defined when you created the release using the create release page. You can only edit the budgeted effort fields.
The work effort default display unit is recorded in hours. The CA Clarity PPM administrator defines the work effort default display unit.
See the Administration Guide for more information.
Follow these steps:
The general page appears.
Defines the budgeted effort to deliver the release.
Displays your organization estimated effort amount to deliver the release.
Copyright © 2011 CA. All rights reserved. | Tell Technical Publications how we can improve this information |