You define scheduling properties for the following purposes:
Best Practice: Set the percent complete calculation method at the beginning of your project and do not change it. Changing the method midway through the project, changes the percent complete values for the project and tasks. The change, in turn, affects other calculations, such as earned value metrics.
Follow these steps:
The properties page appears.
The scheduling properties page appears.
Defines the start date. On lists and portlets, the value for this field is display only.
Default: Current date
Required: Yes
Defines the finish date. On lists and portlets, the value for this field is display only.
Default: Current date
Required: Yes
Specifies if the planned cost dates are synchronized with the investment dates. Selecting the option for a detailed financial plan does not affect the planned cost dates.
Default: Selected
Required: No
Defines the date to include data in time and budget estimates. This date is used in Earned Value Analysis (EVA) calculations, such as Budgeted Cost of Work Scheduled (BCWS) and drives the calculations for costs.
Defines the percent of work that has been completed on the project based on the percentage of completion of the tasks and subprojects. This field is display only and system calculated if the % complete calculation method is set to duration or effort.
Default: 0
Values: 0 through 100
Indicates the level of work completed on the tasks.
Values:
Default: Not Started
Required: Yes
Defines the relative importance of this investment in relation to all other investments. The priority controls the order in which tasks are scheduled during autoscheduling. The priority is subject to dependency constraints.
Values: 0 - 36 (where zero is the highest importance)
Default: 10
Required: No
Indicates the project status.
Stoplight values:
Defines any comments about the project status.
Specifies the method for calculating the percent complete value for the project and tasks.
Note: If you are using CA Clarity PPM with Microsoft Project, or if you are using an external job to calculate % Complete, select manual as the calculation method.
Values:
Summary Task % Complete = Total Detail Task Duration Complete / Total Detail Task Duration
Summary Task % Complete = Sum of Detail Task resource assignment Actuals / Sum of Detail Task resource assignment Effort Detail Task % Complete = Sum of resource assignment Actuals / Sum of resource assignment Effort
Note: If you assign a non-labor resource to a task and the % Complete Calculation Method is set to Effort, the effort and actuals for that resource are ignored in the calculation.
Default: Manual
Specifies if team staff members can record the time they spent on this project on their timesheet.
Default: Selected
Indicates the tracking method used by resource assignments to enter time spent on project tasks.
Values:
Default: Clarity
Defines the charge code against which transactions for the project are charged. If you also define task-level charge codes on timesheets, then the task charge codes override this code.
Defines the set default OBS unit that is used when you add team staff members to this project. This OBS unit more fully describes a staffing requirement, and can be a resource pool, a specific location, or a department. By mapping roles with OBS units and resource managers, the roles can be filled more accurately. The default staff OBS unit is used during capacity planning for analyzing demand against your capacity using the staff OBS as filter criteria.
See the Resource Management User Guide for more information.
Example:
Use the OBS to find out if you have enough capacity for programmers in Atlanta to fulfill the demand for programmers in that location.
Specifies to have requisitions approved before being booked.
Specifies the pool of resources allowed when assigning resources to tasks.
Values:
Default: Resource Pool
Required: Yes
Defines the assigned reporting period for this project. Set the period if your organization uses earned value management methodology for measuring project performance. This field becomes locked (read only) the first time the Update Earned Value History job generates historical data for the project.
Default: Unlocked
See the Administration Guide for more information.
Defines the default earned value (EV) calculation method used when calculating EV. This method sets the default if you have not selected an EV calculation method for the task.
Values: Percent Complete, 0/100, 50/50, Level of Effort, Weighted Milestones, Milestone Percent Complete (PC), and Apportioned Effort (AE)
Default: Percent Complete
Defines the Budgeted Cost of Work Performed (BCWP). This value overrides the system-calculated BCWP and is used for all earned value (EV) metrics that are based on BCWP.
Best Practices: If your company does not use CA Clarity PPM to calculate EV but uses an external system, manually enter a value in this field. If you do not enter a value in this field, then the system-calculated value for BCWP is used in all EV calculations.
Displays the system-calculated value of Budgeted Cost of Work Performed (BCWP). The value is calculated and recorded when you baseline a project, or when you update earned value totals. BCWP is also referred to as the earned value (EV). BCWP represents the amount of the budgeted cost (BAC) completed based on performance as measured using the Task EV Calculation method.
Calculations are made based on the level at which the calculation is made. BCWP is calculated at the following levels:
Current Baseline Required: Yes
Displays the date the earned value was last updated.