The investment team detail page lists planned and committed allocation for an investment by resource by time period in a column graph format. This view helps you determine if a resource is overbooked or under booked and by how much. You can also ascertain the availability for a resource for an investment.
Data on the detail page appears by resource, allocation, and time period. Scrolling over a time period displays a note providing you with a brief summary of what you see. The time period columns are, by default, set to weekly, and always start with the current week. The allocation color code works as follows:
You can change many of the time-related values on this page by configuring the default view to display the allocations as a number graph.
See the CA Clarity Basics User Guide for more information.
Follow these steps:
The team detail page appears.