You can shift or scale all or a portion of the resource allocations in an investment by moving resource allocations back and forward in time. As you move data, segmented allocation dates are kept intact, even when the percent allocated for each segment changes. Shifting a resource allocation is useful when you want to push the investment allocations beyond the allowable time-scaled view, which can only extend for six months.
Use the Shift Allocation option that is available on the investment team staff and team detail pages.
As an example, consider an allocation that starts on May 1, continues at its default rate of 100 percent through the end of May. In June, the allocation is reduced to 50 percent. If you shift the allocation to start on June 1, it will go from June 1 through July 2 (for 31 calendar days) at 100 percent. Then through August 2 the allocation is at 50 percent. You can also shift allocations for time spans that contain no segments.
Follow these steps:
The investment team staff page appears.
The shift allocation page for that resource appears.
The changes you made are reflected in the Allocation column on the investment team staff page.
| Copyright © 2011 CA. All rights reserved. | Tell Technical Publications how we can improve this information |