For each role added to the portfolio, only resources associated with the role as their primary role are factored into the total capacity for the duration of the portfolio.
Example
Suppose you are evaluating the capacity for the Developer role. If one developer works full-time at 2080 hours and another works half-time at 1040 hours, the aggregated total capacity for the duration of the portfolio (one year in this case) is 3120 hours. The capacity depends on the date range in the portfolio.
| Copyright © 2011 CA. All rights reserved. | Tell Technical Publications how we can improve this information |