Project Baselines Portlet

The Project Baselines portlet displays a line graph that charts the baseline activity against the usage or hours worked on the project. The X-axis displays monthly periods and the Y-axis displays cumulative project hours. A line appears for each baseline on the project and the current project plan.

Status Report Indicators Portlet

The Project Status Reports portlet displays status report indicators from the most recent status report, based on report date.

Note: To display information in this portlet, a project status report must exist.

The following fields display on the portlet:

Overall Status

Displays a stoplight indicating how the project is doing overall. The metric is based on the Overall Status stoplight in the status report.

Stoplights:
Report Date

Displays the date that the status report was created. Click the date to view the status report properties page.

Project Manager

Displays the project manager name.

Schedule

Displays a stoplight indicating whether or not the project schedule is on track. The metric is based on the Schedule section in the status report.

Stoplights:
Scope

Displays a stoplight indicating whether or not the project scope is on track. The metric is based on the Scope section in the status report.

Stoplights:
Cost and Effort

Displays a stoplight indicating whether or not the project cost and effort are on track. The metric is based on the Cost and Effort section in the status report.

Values:
Status Reports

Displays an icon that links to the status reports of the project.