Create a Status Report

You can create a status reports to track the progress of a project or program.

Follow these steps:

  1. Open the project or program.

    The properties page appears.

  2. Open the Properties menu and click Status Reports.
  3. Click New.

    The create page appears.

  4. Complete the following fields:
    Status Report Name

    Defines the name of the status report.

    Report Date

    Displays the date the report was created.

    Status Report Update

    Displays the overall project or program status including the latest updates.

    Key Accomplishments

    Describes the main accomplishments or deliverables for the reported period.

    Upcoming Activities

    Describes the upcoming activities.

    Schedule Status

    Specifies a stoplight indicating the schedule status for the project.

    Stoplights:

    • Green. The project or program is on track.
    • Yellow. The project or program has minor variance from the schedule.
    • Red. The project or program has significant variance from the schedule.
    Current Phase

    Displays the current phase of the project or program.

    Next Milestone on Track?

    Indicates if the next milestone is on track.

    Default: Cleared

    Variance Explanation

    Provides an explanation for a variance in the project or program schedule.

    Limits: 2000 characters

    Scope Status

    Indicates the status of the project or program scope.

    Stoplights:

    • Green. The project or program scoping is on track.
    • Yellow. The project or program scoping has minor variance.
    • Red. The project or program scoping has significant variance.
    Scope Change Required?

    Indicates if a change in the project scope is required.

    Default: Cleared

    Deliverable Scope Changed?

    Indicates if the scope of the project deliverable has changed.

    Default: Cleared

    Project Objective Changed?

    Indicates if the project objective has changed.

    Default: Cleared

    Change Explanation

    Provides an explanation for a change in the project objective.

    Limits: 2000 characters

    Cost and Effort Status

    Displays the cost and effort status of the project.

    Stoplights:

    • Green. The cost and effort status is on track.
    • Yellow. The cost and effort status has a minor variance.
    • Red. The cost and effort status has a significant variance.
    Review Approval Problems?

    Indicates if the project is encountering any review approval problems.

    Default: Cleared

    Staffing/Availability Issues?

    Indicates if the project is encountering staffing availability issues.

    Default: Cleared

    Project Affected by External Factors?

    Indicates if external factors affect the project.

    Default: Cleared

    Cost and Effort Explanation

    Provides an explanation for the cost and effort status.

    Limits: 2000 characters

  5. Save the changes.

    The status report is created.