Set Baselines

Use the Multiple Baselines dialog box to set baselines and to re-baseline your project. This dialog box lists the baselines that you have already set on the project. When you set a new baseline, its default name is Baseline1 and it is marked as the current baseline. If the project already has a baseline named Baseline1, then when you set a new baseline its name is Baseline2. You can edit the name after you capture the baseline.

You must select all levels of the WBS to re-baseline your project. When you re-baseline tasks that have changed—such as changes to a resource's ETC—the data is not rolled up to the summary task level. Data, however, is rolled down to a phase's tasks when you re-baseline at the summary task level.

To set a baseline

  1. Select Tools, Baselines, Multiple Baselines.

    The Multiple Baselines dialog box opens.

  2. Click New.

    A new baseline is set and is displayed in the list.

  3. Click OK.

    The Baseline dialog box closes.

More information:

Baseline Projects

Baselines and Earned Value Computations

Display Baseline Data in Views

Edit Baselines

Rebaseline Projects

Multiple Baselines with Master Projects and Subprojects

Clear Baseline Values

Delete Baselines