Previous Topic: Print Task Dependencies

Next Topic: Dependency Relationships Between Master Projects and Subprojects

Display Dependency Relationships

You can display dependency relationships on the Dependencies grid in the Dependencies tab on the Task Properties page or from a Gantt chart view.

Before you can create dependency relationships from a Gantt chart view, you should first be able to view the relationship in the Gantt chart. When you show dependencies, the Gantt chart area of the view displays connecting arrows between tasks that have dependency relationships.

Note: To display the dependency, first add the Task Name or Task ID field name to the view definition and place the fields in a column preceding the Type, Lag, Lag Type, and Project columns.

To display dependency relationships in a Gantt chart

  1. Double-click anywhere on the Gantt chart.

    The Gantt dialog box appears.

  2. Select the Show Dependencies check box, and click OK.

    The Gantt dialog box closes. The established dependency relationships display in the view.

More information:

About Task Dependencies Properties