Previous Topic: Performance Indices

Next Topic: About Analyzing Projects with Current Baseline

Percent Complete Indices

Use the % Complete Calculation Method field (on the Description tab of the Project Properties dialog box) to specify how Open Workbench computes the percent complete value. Earned value data is used against the Budget at Completion (BAC) to calculate the percent complete indices.

The percent complete value is used in earned value calculations such as the following:

Periodic reviews of these measures can help you uncover trends over time as your project progresses. Examples of percent complete index fields include Perform % Complete, Schedule % Complete, and Actual % Spent.

To view this data, first add the field to a view.

More information:

Analyze Projects with Earned Value Variances

Define Project Description Properties

Define Open Workbench Default Options

Analyze Projects with Earned Value Variances

View Task Percent Expended Amount