Use the Resources tab on the Task Properties dialog box to enter a resource's ETC on a task. You can also define a resource's ETC on a task from the Schedule spreadsheet view. Enter hour or day ETC values depending on the Default Unit setting you defined on the Defaults tab on the Options dialog box. If a task has an ETC value that exceeds zero, you cannot set the task's status to "Completed".
Note: If the resource's loading pattern is set to fixed you can only enter ETC in a tabulated view.
You can also remove a resource's ETC on a task using this tab. If you are using Open Workbench with CA Clarity PPM and you need to remove ETC that you have posted to a task that has not started, you must do this in CA Clarity PPM by adjusting your posted timesheet.
If you are using Open Workbench with CA Clarity PPM, you must define a billing rate for cost-based resources in CA Clarity PPM. If the resource does not have a defined billing rate, in CA Clarity PPM, add an entry to the resource's rate matrix and run the Rate Matrix Extraction job.
Note: See the Administration Guide for more information.
To define a resource's ETC on a task
The Resources tab on the Task Properties dialog box opens.
The Task Properties dialog box closes.
To define a resource’s ETC on a task from a view
The project schedule is displayed in a spreadsheet view.
The resource's ETC on a task is changed.