A Key Task is a task that you consider to be of key importance to the project. When you mark a task as a key task, its status does not impact any other Open Workbench behavior. Use the Key Tasks tab on the Project Properties dialog box to:
To edit a key task, edit the task's fields in a spreadsheet view, such as the Gantt Chart view.
To view a project's key tasks
The Description tab on the Project Properties dialog box opens.
A list of the project's key tasks display.
Defines the key task's external ID.
Defines the key task's status.
Choices: Not started, Started, or Completed
Defines the key task's name.
Defines the project name associated to the key task.
Defines the date the key task is scheduled to finish.
Note: You can edit the finish date provided you have not assigned a resource to the task and the task is a fixed duration task.
Defines the date the key task is scheduled to finish based on the current baseline.