View Tasks Marked as Key Tasks

A Key Task is a task that you consider to be of key importance to the project. When you mark a task as a key task, its status does not impact any other Open Workbench behavior. Use the Key Tasks tab on the Project Properties dialog box to:

To edit a key task, edit the task's fields in a spreadsheet view, such as the Gantt Chart view.

To view a project's key tasks

  1. Select Project Properties from the application menu at the top left corner of the window.

    The Description tab on the Project Properties dialog box opens.

  2. Click the Key Tasks tab.

    A list of the project's key tasks display.

  3. View the following key task data, and click OK:
    ID

    Defines the key task's external ID.

    Status

    Defines the key task's status.

    Choices: Not started, Started, or Completed

    Name

    Defines the key task's name.

    Project

    Defines the project name associated to the key task.

    Finish

    Defines the date the key task is scheduled to finish.

    Note: You can edit the finish date provided you have not assigned a resource to the task and the task is a fixed duration task.

    Baseline Finish

    Defines the date the key task is scheduled to finish based on the current baseline.

    The Project Properties dialog box closes.

More information:

Update Project Data

Define Tasks as Key Tasks

Task Status and Percent Complete