How to Make Voucher and Resources Types Available for Processing

The following voucher types are used to categorize transactions by resource type for transaction entry:

To make labor, materials, equipment and expense resource types available for transaction processing, do the following:

  1. Create a resource (as needed) for each resource type and financially enable them.

    See the Resource Management User Guide for more information.

  2. (Optional) Create a cost/rate matrix for each labor type.
  3. Add the resource as a team member to the investment.

    See the Project Management User Guide for more information.